Foothill Gold Line Community Groundbreaking Ceremony
Saturday, December 02, 2017
Hits : 232
by This email address is being protected from spambots. You need JavaScript enabled to view it.

SAVE THE DATE!

The Glendora to Montclair project will break ground on December 2, 2017 and is anticipated to reach completion in 2026. After groundbreaking, the first two years of the project will be spent relocating utilities, conducting pre-construction activities, finalizing engineering, and hiring a design-build contractor. A contractor is anticipated to be hired in late-2018 and major construction is not anticipated to start until 2020.

DATE: Saturday, December 2, 2017
LOCATION: Citrus College, Glendora

Details to be available soon at www.foothillgoldline.org